Microsoft Project 2007 Work Week Defiition

Q: Microsoft Project 2007 Work Week Defiition

Hello all,

I am new to Microsoft Project 2007 and have a question regarding how this software defines a work week.

I have created a new calendar that is a 6 day work week and 60 hours a week for a project that I am working on. Thus, I know how to change the working time, the default work week, and under the "options" tab in the "change working time" menu I have changed the defaults to match what my calendar has for starting and ending times, etc.

My question is since I have changed the work week to start on Monday, if I start a task on a Monday and assign it a duration of 1 week, the task does not end until the next Monday. Since I have defined a 6 day work week, a week to me seems like it would be 6 full working days, and if it started first thing Monday it would end at the time I assigned on Saturday as the close of work. If I assign the task a duration of 0.98 weeks it ends on the Saturday that I wish it would end on, it does in fact end on Saturday.

If you change the view to "calendar" a task that starts on a Monday and has a duration of 1 week, or any round number of weeks, will continue through all Sundays and into Monday at the time that I set work to start on Monday.

How do I make a week in my situation last only 6 working days? (IE how can I start a task that will take one week, start on a Monday and have it end on Saturday at the close of business?) Obviously tasks that are constrained to start directly after this task that end on Saturday evening I would like them to start the next Monday since my work week is Mon-Sat.

Thanks for your time.

RELEVANCY SCORE 200
Preferred Solution: Microsoft Project 2007 Work Week Defiition

I recommend downloading and running Reimage. It's a computer repair tool that has been proven to identify and fix many Windows problems with a high level of success.

I've used it in the past to identify and fix everything from blue screens (BSOD's), ActiveX errors, corrupt files and processes, dll/exe/sys errors, recover lost memory, Windows update problems, defragging, malware removal etc.

You can download it direct from this link http://downloadreimage.com/download.php. (This link will automatically start a download of Reimage that you can save to your computer.)

A: Microsoft Project 2007 Work Week Defiition

Just to clarify, if you have a task with the Project standard calendar with a duration for 1 week and start it on a Monday, it will finish on that weeks Friday. If you then assign a task that is start to finish constrained to the first task, it will start on the next Monday after the first task finished the previous Friday. My problem is that since I changed the calendar, the tasks run through the non working days and up to the start of business to the next day.

Thanks

Read other 1 answers
RELEVANCY SCORE 72

The original file was created in 2010 and saved in 2007 format - sent to me - I worked on it saved several times but when finally exited did not save. When reentered the file is blank however on properties shows it is still 655kb.

A:Microsoft project 2007 file

Any chance the .docx color is set to white?

Read other 1 answers
RELEVANCY SCORE 72

OK, so, I'm in Computer Science (IT) so I have an entire course on how to use Microsoft Project 2007. They make us buy a little how-to book. I'm following that book as an homework.

So here is the problem. From the Resource Sheet, I choose a resource. Then, I go to Tools -> Change Working Time. I then click on the tab "Work Week". Then, I create a new exception for the resource. Then, in the boxes next to it, in the drop boxes, there's calendar to set when it begins and where it ends, right? Each time that I want to set the end day, Microsoft Project 2007 crashes automatically. It happens sometimes on the start day too.

Anyone can help with that?

P.S Word, Access, Excel and PowerPoint are installed too, but in French. Project 2007 is in English.

EDIT

Ah... Project doesn't like it when we select Januray 1st to December 31st when we are January 10...

Read other answers
RELEVANCY SCORE 71.2

Dear all,
I have included tasks in a project with theorethical starting dates.
Now if I go to tracking & I input the actual start, my bar representing the duration of my task on the GANTT chart will be shifted accordingly.

What i need to know is is there a way that i could see on my gantt chart both the original & actual bars one under the other so i can have a visual comparision of the shifting in my project after i correct by putting actual start values...

Thx
 

A:Solved: Microsoft project 2007 technical ?

after TOOLS - TRACKING - SAVE BASELINE - ENTIRE PROJECT,
a set of grey bars identical to the original planned bars should appear but they aren't.
Even after VIEW-TABLE:ENTRY-MORE TABLE-BASELINE (ensuring that task is selected), I am unable to view these grey baseline which could answer my question if resolved.
 

Read other 2 answers
RELEVANCY SCORE 71.2

Hello, Vista forums experts! Got a fairly simple question but I wanted expertise before I proceeded. Here's the basics:

1. I am running Vista Home Edition SP1 and Office 2007 Professional. Everything is fully up-to-date with patches, etc.

2. In the summer, I installed Office 2007 Professional that works perfectly (or as perfect as it can be).

3. Two months ago, I took a college course that required Microsoft Project 2007 Professional to be installed on my PC as a 60-day trial.

4. The course has ended and I want to uninstall ONLY Project, but I am worried that the uninstallation may strip away parts or features of Office that I do NOT want to uninstall. (ie: Word, Excel, Outlook, etc...)

5. Is it safe to uninstall or should I just leave it on my PC? (It's not like I'm hurting for the hard disk space).

Any thoughts or methods?

Thanks so much!

Travis

Read other answers
RELEVANCY SCORE 70.4

Hello, I have a user here who cannot open all project files. Upon trying to open it, Project 2007 crashes. When opening it again, the attached screen shot shows up. I have started project first, then removed the file from the disabled items list, and it still crashes. Everyone else is able to open this file. I have saved the file to his desktop, still crashes. I have logged on as myself on his computer, still crashes. I uninstalled Symantec Endpoint Protection, still crashes. I uninstalled, cleaned the registry, then reinstalled Project, still crashes. I updated the rest of his Office suite to 2007, with service pack 2, still crashes. I installed service pack 2 for Project, still crashes. I have run Microsoft diagnostics, but it doesnt find anything. So I have not been able to figure this out, and I have run out of ideas. I want to avoid as much as possible a full rebuild on this machine because of all the user settings and software that he has installed on this. Does anyone have any other suggestions as to what might be causing this to crash? Thank you

Read other answers
RELEVANCY SCORE 69.6

A few years ago I got a copy of MS Project Standard 2007 from my daughter's school which I installed and activated on my new office PC when I built it, using a one time only product key (Academic Promotion).
(FYI - upon careful reading of the license I saw that the software is for a current student or teacher - or a family member of a qualifying student, which was true at the time and is still true until May of this year)

Now I am considering upgrading this PC to Windows 10 in a clean install.

My understanding is that I will lose Project 2007. I will not be able to activate it again on my "new" PC and I will have to revert back to my previous Project program or buy a new/old copy of 2007 (and factor this additional cost into my decision making).
Am I correct?

Second question: since I already have the installation media, is there a way to just pay Microsoft for a single license - new product key without having to go through the whole dance of buying another DVD?
I'm not interested in newer versions, and especially not interested in paying $25/m for Project 365.

Read other answers
RELEVANCY SCORE 64.4

Does anyone know how I can open a MS Project 2007 file in MS Project 2010. The file that was sent to me is .mpp and created in 2007 but I own 2010 and it says Project cannot open file.
 

A:Can't Open MS Project 2007 file in MS Project 2010

You will need to convert the file or it will be displayed in Compatibility Mode with reduced functionality. Then, you can resave the project as a 2010 format.

Opening Project MPP files from different versions

 

Read other 3 answers
RELEVANCY SCORE 63.6

why microsoft virtual pc 2007 and microsoft vitual cd/dvdv do not work on windows 10 and do you have alternative programs

Read other answers
RELEVANCY SCORE 63.2

MS Project Server files are saved in Project 2007 format .mpp and then re-opened in MS Project 2010. When the file is opened in MS Project 2010 the progream switches to compatibility mode but there are no tasks or project details - it is a blank schedule. I can open the same file in MS Project 2007 at home, but cannot open it at work on my laptop in MS Project 2010 (opens but is blank).

Any ideas what the issue might be? Belwo are my laptop details.

Tech Support Guy System Info Utility version 1.0.0.2
OS Version: Microsoft Windows XP Professional, Service Pack 3, 32 bit
Processor: Intel Pentium III Xeon processor, x86 Family 6 Model 23 Stepping 10
Processor Count: 2
RAM: 3535 Mb
Graphics Card: Mobile Intel(R) 4 Series Express Chipset Family, 1024 Mb
Hard Drives: C: Total - 76316 MB, Free - 26108 MB;
Motherboard: Dell Inc., 0W612R
Antivirus: VirusScan Enterprise + AntiSpyware Enterprise, Updated: Yes, On-Demand Scanner: Enabled
 

A:Cannot see Project 2007 files in Project 2010

http://www.mpug.com/Pages/MPUGForums.aspx?action=ViewPosts&fid=7&tid=709
 

Read other 1 answers
RELEVANCY SCORE 62.8

I'm using a Microsoft Project trial but as I think you can see in this screenshot, it isn't looking good:

It seems to have its idea of the length of a month incorrectly calibrated so that a month equates to a week. Similarly, weeks are shorter than they're supposed to be. What should I do?

A:MS Project: Month = Week?

Hi

Try removing the end/finish dates - see if that works

Read other 7 answers
RELEVANCY SCORE 58.8

I have old and new reference products (dictionaries etc.) some of which are only compatible with Windows98

I have both XP and Vista installed on two seperate hard drives and am switching between them using the bios.

I downloaded Microsoft Virtual PC 2007 (both 64 bit and 32 bit) but couldn't get either working under either operating system.

Apparently Vista home premium isn't supported, but it's also telling me that Windows XP Home Edition (Version 2002, Service Pack 3) is not a supported environment when I try and install it, and I don't understand why since it's listed as being supported at the Virtual PC Support page.

I feel like the only way I'm going to be able to get all the software I want running at the same time is to build a second PC and run them side by side.

Surely there's an easier, less expensive and more economical solution?

Every step I take towards the solution seems to move me back two, so help would be very appreciated. Truly.

A:How can I get Microsoft Virtual PC 2007 to work?

Maybe you should try VirtualBox, there is a GPL version.

Read other 7 answers
RELEVANCY SCORE 57.6

my microsoft 2007 trial is not working because i modified some changes to it by going to "start" button, click "run", type "regedit", went to HKEY_LOCAL_MACHINE/SOFTWARE/Microsoft/Office/12.0/Registration/{91120000-0014-0000-0000-0000000FF1CE and deleted "product id" and "digital id" and then i closed it. Then i clicked "start", went to "run", typed in: C:\Program Files\Common Files\Microsoft Shared\OFFICE12\Office Setup Controller\Proof.en, then i opened the "proof.xml" in notepad, then i changed the section at the bottom where it says </Feature>

<Feature Id="SetupXmlFiles" Cost="1248">

<OptionRef Id="alwaysInstalled"/>

</Feature>

</Package> and i changed "alwaysinstalled" to "neverinstalled". then my microsoft doesnt work. I can open my stuff but i cannot type or do anything. Also i cannot uninstall the microsoft and i cannot install or reinstall any new or old microsoft office programs.

 




RELEVANCY SCORE 57.6

I know how to use bullets, but if you tab in the bullets, it will stay tabbed throughout the entire document unless you set up tabbed bullets again. When I try to backspace to go back to left alignment, it will delete the bullet and still stay tabbed. Basically what I am asking is after you do a tabbed bullet, how do you go back to aligning the bullets left again?

A:How to make bullets work in Microsoft Word 2007

Try shift-tab instead of Backspace to shift the tab to the left.

Read other 7 answers
RELEVANCY SCORE 57.2

I recently changed to Bell as ISP with my new email address [email protected] and Outlook doesn's work my computer info is
Tech Support Guy System Info Utility version 1.0.0.2
OS Version: Microsoft Windows 10 Home, 64 bit
Processor: Intel(R) Core(TM) i7-4790 CPU @ 3.60GHz, Intel64 Family 6 Model 60 Stepping 3
Processor Count: 8
RAM: 8130 Mb
Graphics Card: AMD Radeon R7 240, -2048 Mb
Hard Drives: C: Total - 937559 MB, Free - 720781 MB; D: Total - 14341 MB, Free - 1818 MB; F: Total - 238472 MB, Free - 30157 MB;an you offer any
Motherboard: Hewlett-Packard, 2AF7
Antivirus: Kaspersky Total Security, Updated and Enabled
The error message reads...failed to update headers. Can you offer any assistance?
 

A:Microsoft Outlook 2007 doesn't work with new email address

What error message are you getting?
 

Read other 2 answers
RELEVANCY SCORE 56

my microsoft 2007 trial is not working because i modified some changes to it by going to "start" button, click "run", type "regedit", went to HKEY_LOCAL_MACHINE/SOFTWARE/Microsoft/Office/12.0/Registration/{91120000-0014-0000-0000-0000000FF1CE and deleted "product id" and "digital id" and then i closed it. Then i clicked "start", went to "run", typed in: C:\Program Files\Common Files\Microsoft Shared\OFFICE12\Office Setup Controller\Proof.en, then i opened the "proof.xml" in notepad, then i changed the section at the bottom where it says </Feature>

<Feature Id="SetupXmlFiles" Cost="1248">

<OptionRef Id="alwaysInstalled"/>

</Feature>

</Package> and i changed "alwaysinstalled" to "neverinstalled". then my microsoft doesnt work. I can open my stuff but i cannot type or do anything. I also cannot uninstall it and cannot install any new or reinstall any old microsoft office programs. HELP PLZ PLZ PLZ!

 




RELEVANCY SCORE 54

I'm a technical support engineer for a major IT company supporting a major client and today I came across a issue that i find hard to troubleshoot. When the client launches MS Project Pro 2007 and goes to Tools-Enterprise Options-Open Enterprise Resource Pool, the resources appear but as soon as he clicks the open button in the Resource Centre it comes up with a message:
"To perform this action, you need Microsoft Office Project Professional 2007. If you are using this version, verify that a correct account for the computer running Project Server has been set up and selected. To verify the account, on the Tools menu, click Enterprise Options and then click Project Web Access Accounts. If you still cannot perform this action, contact your server administrator to ensure that enterprise features have been enabled on Project Server."

Please help
 

Read other answers
RELEVANCY SCORE 54

Is there anyone out there that knows how to create a Gantt Chart? I'm having the worst time trying to figure it out!

A:Ms Project 2007

Does this Project 2007 Help and How-to article help? If not, can you give us a little more information, please. What is it you are trying to do and having difficulty with? What things have you tried and failed to make happen? The more information you can give us, the more we can help.Be (MS Project 2007) SafeDa Bleepin AniMod, Animal

Read other 3 answers
RELEVANCY SCORE 54

I was trying to learn how to work in MS Project 2007 from the net but I did some changes in project and now my Task Pane is gone, Can any one help me bring back the task pane.
 

Read other answers
RELEVANCY SCORE 53.2

I have recently purchased Office 2007 and Project 2007. I can open and save a file in project successfully however if I attempt to open a previously saved project file the application crashes. I have ran diagnostics and this is not finding any problems, I have also sent numerous email to Microsoft support desk but have not yet had a response. Operating system is

Microsoft Operating System
Genuine Windows Vista® Home Premium SP1- English

Regards

Eileen
 

Read other answers
RELEVANCY SCORE 53.2

Within PWA, I went to the home page of a project. At the Home Page of the project, I added the time sheet option through Web Parts and the time sheet now shows up on my project home page. Life is good. As a test, I added 1 hr to the sick time task. I recaluated and it worked. I saved the change and I received the dialog box--> While communicating with the Project Server an error occured. Check connectivity with your administrator to determine if further action is necessary. So, it lets me add TimeSheet to the Project Hoem page, but the Tiem sheet function doesn't work.
 

A:Project 2007 - PWA - Web Parts

The Project Server uses the SQL server on the backend if I recall. Have your network guy check to make sure the connection between the two are ok. If that is not the case make sure the webserver is interfacing with the project server as well.
 

Read other 1 answers
RELEVANCY SCORE 53.2

When I try to open my .mpp files that I created with Project 2010, I get an error message indicating that the 2007 version (I doesn?t have Office 2007 on my PC) is trying to open them and that I need to install a converter. Any suggestions on how I can make 2010 to open my Project files? (I'm running Windows 7, if that matters.)

Read other answers
RELEVANCY SCORE 53.2

I am having a problem with MS Project 2007 crashing whenever you try and perform a function within it. The application will load, an will even allow you to connect to your Project Server. However, whenever you try to do anything beyond that (ex: open a project schedule), the application will crash.

I have tried repairing, and re-installing Project. I have also tried un-installing & re-installing all of Office (with reboots in-between each step, just to be sure). Project has all of the available updates installed, including the Office 2007 SP1. It is running on a WinXP machine.

Any suggestions would be appreciated.

Thanks!
--Mike
 

Read other answers
RELEVANCY SCORE 52.8

When we are trying to install this patch(KB968850) on the Microsoft project server 2007  we are getting the fallowing error.
The detection failed ,This can be due to corrupted Installation database.
When we are trying to install any hotfixes we are getting the same error.
When we observed in the event viewer we are gettin the event id as
event id: 11708
source: msiinstaller
description: Microsoft Office Project Server Application Server -- Installation failed.
I have attached the error
Could anyone can help us regarding this issue

A:MS Project Server 2007 issue

Alternative method (this does not apply for Project 2007 and later versions) only for MS Project 2003...
 
Save the file in the Microsoft Project Database format:
 
1. Open your problem file (it may help to turn off automatic calculation if the file is reluctant to open).
2. Select File/Save As...
3. Save as type: Project Database (*.mpd) then click Save.
4. Close the file.
5. Re-open it from the .mpd file.
6. Select File/Save As... And save it as an .mpp file again.
 
Look at helpful resources which contain different guides, solutions...
http://www.makeuseof.com/answers/can-recover-microsoft-project-2010-file-wont-open/
http://www.filerepairforum.com/forum/microsoft/microsoft-aa/project/1484-ms-project-2010-cannot-open-mpp-file
https://www.repairtoolbox.com/projectrepair.html Project Repair Toolbox

Read other 1 answers
RELEVANCY SCORE 52.8

I have a scheduling problem which my lack of experience with MS Project won't allow me to resolve.
My project is scheduled from the start. The project is effectively the work of a small team over the course of a year.
I have added to my plan:

Tasks (approx 350)
Durations
Dependencies
Constraints (only the bare minimum where tasks are actually fixed (meetings, events ,etc))
Resources (people only, no real materials to consider)
At this stage the vast majority of the work within the project occurs (as you would expect) at the beginning, or; “As Soon As Possible”.
Given that the work within the project is for a small team, most of the resources appear to be massively over allocated.
I have an idea of when I want the work to be completed during the year but have attempted and discarded the option of setting “Start No Earlier Than” or Finish No Later Than” constraints on my tasks as because:

Doing so still didn’t give me the schedule I wanted (was still over allocated even after levelling)
I want my plan to be as flexible as possible as I move forward. It may well be that some work finishes ahead of schedule and if I’ve set a SNET constraint on a task purely to give an indication of when I think it will/should happen, my plan won’t be able to move accordingly.
Most articles I’ve read on the matter suggest that over-constraining is a bad idea, probably due to the point raised above.
I want MS Project to schedule my tasks for me – I really thought that this was pa... Read more

A:MS Project 2007 - scheduling help required

Hi herebutlost,

Your 1. above says you have used levelling, did you do it manually over the whole project, did you clear previous attempts first ?
Important, did you restrict Levelling to only within slack (if so then remove that restriction).

I suggest this because Levelling is specifically to remove over-allocations.

lol
Hew
 

Read other 3 answers
RELEVANCY SCORE 52.8

I am using the template available from 2007, but I want to have a list of tasks that get done every month, but they may be done each month by a different person. I can't seem to re-use a common task. Does anyone know how to do this?
 

A:Access 2007 Project template

marilyn934, welcome to the Forum.
I never use Templates as I prefer to start from scratch with what the users need, so I don't know what the template does or how it does it.
Does it use a form or report and is it based on a query?
 

Read other 1 answers
RELEVANCY SCORE 52.8

Is there anyone here who knows the in's and out's of Project Server 2007. I am stuck trying to gain access to sites created either thru a browser or Project Pro 2007.
I did the Basic install, which installed and created a new site after installation. It installed SQL express, SharePoint Services, and made the changes to IIS. I am now at the point where I can log on to the default site created PWA (Project Web Access). What I would like to finally get to is create a site called "company name" and be able to connect to it with either Project Pro 2007 or thru Web Access.
I have gone thru MS sites for the past week, and I even bought a book. All say to do what I have already done, but I still can not get Project Pro to even connect to the default site.

Any help or ideas, would greatly be appreciated.
Thanks
 

Read other answers
RELEVANCY SCORE 52.8

Does anyone know of a free MS Project 2007 viewer??
 

A:Free Project 2007 viewer

Hi there,

No viewer available. You can try it online (via web browser) or download a free trial. It is a very large and very expensive program. Look here:

http://office.microsoft.com/en-us/project/default.aspx
 

Read other 2 answers
RELEVANCY SCORE 52

Hello,

I would like to know what are some potential compatibility problems between MS Project 2003 and MS Office 2007? Will I run into any known problems after installing them on the same machine? I appreciate your help!

-Chris McCarthy

A:Project 2003 and MS Office 2007 compatibility

well the only thing you can do is try.. i have never used MS project before so; i would just try it and if it does not work uninstall on of them

Read other 2 answers
RELEVANCY SCORE 52

I just finished an upgrade install of 10 from 7. I tested all programs and only had a problem with Avast and Microsoft Office Project 2007. The Avast problem is repaired.

I double click to start the program > the "Office Project 2007" splash screen shows > the spinning orb blinks and it sits there for 15-20 seconds > then a "Configuration in Progress" window comes up > then a "Please wait while Windows configures MS Project" windows comes up > then I get an error : "There is not enough memory to complete this operation" > and that's it.
(There is plenty of memory)

I inserted my installation DVD and tried a Repair. No joy.

I've tried to start Project in Safe Mode. No joy.

Wondering what to try next. Any ideas?

A:MS Project 2007 does not start after Upgrade Install

OK, so the solution was pleasantly simple.

I uninstalled Project 2007 and reinstalled it, using my (one-time) product key.
It installed, worked fine, and was activated immediately. It even retained all of my settings preferences and previous files list from before.
(You call that an uninstall? Yikes!)

Office 2003 had a brief hiccup after uninstalling Project 2007, but it was resolved internally quickly.

Very weird, but all is good now.

Read other 0 answers
RELEVANCY SCORE 52

Hi all. My daughter's school offered students a free copy of MS Office Project Pro 2007. She has no use for it but I do, so I snagged it along with the installation product key.

I installed it on my current desktop to check it out - make sure I can open my old Project 98 files, etc. Works great! But I have not activated it yet (22 more starts to go!).

This version has a One Installation on One Machine license.

Now I plan on building a new machine in the next couple of months and I will want Project 2007 on that machine. So my question is: should I wait and install & activate once I'm on the new machine?

Some high end programs have an option to deactivate the installation on the old machine and reactivate on the new machine, allowing only one installation on one computer. Is this the case with Office progs? Or are they serious: installed on one computer - give it away with the computer when you upgrade?

Educate me please!

A:MS Office Project 2007 Pro Activation query

Dear TVeblen

Let me quote you Microsoft Software License Terms (MSLT) for 2007






Quote:
15. REASSIGN TO ANOTHER DEVICE. You may reassign the license to a
different device any number of times, but not more than one time every 90
days. If you reassign, that other device becomes the “licensed device.”
If you retire the licensed device due to hardware failure, you may
reassign the license sooner.


Thus, IMHO you shouldn't have any troubles reassigning this copy to another device.
There is no procedure for MS OFFICE deactivation. One should simply uninstall software from first computer and then reinstall and activate it on the second.
Should you ever experience any troubles, you can always reactivate vie phone.

Read other 2 answers
RELEVANCY SCORE 52

Hi.

I have an existing project 2007 file with some 550 lines total making up about 7 projects.
When I go to add an additional project (via cut and paste) with a total of 250 lines... project hangs
and sits for a very long time (20min) before it returns with nothing inserted....

Any ideas on how to fix this ????
roman

Tech Support Guy System Info Utility version 1.0.0.1
OS Version: Microsoft Windows XP Professional, Service Pack 3, 32 bit
Processor: Intel(R) Core(TM) i7 CPU Q 820 @ 1.73GHz, x86 Family 6 Model 30 Stepping 5
Processor Count: 8
RAM: 2999 Mb
Graphics Card: NVIDIA Quadro FX 880M, 1024 Mb
Hard Drives: C: Total - 244198 MB, Free - 63942 MB; D: Total - 61043 MB, Free - 4020 MB; J: Total - 953197 MB, Free - 562088 MB;
Motherboard: Hewlett-Packard, 1521, KBC Version 32.33, CND1021G04
Antivirus: McAfee VirusScan Enterprise, Updated: Yes, On-Demand Scanner: Enabled
 

Read other answers
RELEVANCY SCORE 52

got a trial version ms project 2007 with textbook. Prof said if expires reinstall it. tried uninstall and reinstall. not letting me do the reinstall. says expired.
i purchased the office 2003 without project but need project for my class.

A:can't reinstall trial version ms project 2007

Usually once a trial has ended you cannot reinstall it, otherwise, trial periods would go on forever. I could be wrong, but I believe it is against forum rules to help you circumvent that

Read other 2 answers
RELEVANCY SCORE 52

I was not looking and typing away a question in calendar search and I ended up somehow switiching the view to Day from Week. It has always been on week where I want it.

I changed the View setting to week and it seemed fine, but everytime I leave calendar and navigate to mail or contacts and work there and then come back to calendar it is back in the Day View setting............almost like it defaults to there. I have looked around and can't figure out how to lock the Calendar Week View setting like I had before. Ideas?
Thanks,
G
 

A:Outlook Calendar 2007 keeps going back to Day view from Week

Well, after still trying many things, I found when I changed the view from day/week/month to day/week/month with auto preview that it stayed locked on week view. Not sure why, but seems to have worked. I will monitor it a while and if it seems ok then I will mark the thread solved.
G
 

Read other 1 answers
RELEVANCY SCORE 51.6

I am looking for some help with MS Project 2007.

I have installed Project 2007 in a stand-alone environment (advanced setup) for evaluation purposes & have been trying to find documentation which explain how to setup & configure email notifications.

Despite browsing through various Technet articles & Google searches my attempts so far have been unsuccessful.

Can someone provide any documentation, links, or details on what I need to do?

Thanks in advance
 

Read other answers
RELEVANCY SCORE 51.6

I have used the project managmenet template that is available to you when you open Access 2007. I decided to make it a File Managmenet system instead and renamed the Project table Files, and the Project List form to File List form. Although I have changed the autoexec macro to open the File List if the Getting Started screen un-checked, I get an error message every time I open the project saying the Project List form name is still in a macro somewhere and it has been renamed or deleted. The program then opens as it should, I just get that error message every time I start. There are no other macros in the template and I can't find any VBA programing where I can change the form name to File List. I do not get a macro name where the error is, so it must be in an embedded macro, but I can't find it for the life of me. Need to solve this before I go nuts! Help!!
 

A:Solved: Access 2007 Project Management Template

Read other 10 answers
RELEVANCY SCORE 51.6

After i installed MS Project 2007, everytime i open Outlook 2003, a window will pop saying that Outlook needs configuring. It will take a few minutes and finish and then disappear. Does anyone have any idea how to fix this issue? Any help is appreciated.

Sean
 

Read other answers
RELEVANCY SCORE 51.6

I have a custom category to apply to my project plan, but more than one category can apply to each task. Essentially I need a multiple select drop down list.

I can create the custom field and the drop down list, but it only allows me to choose one option per task.

Does anyone know if it's possible to do this?

Thanks in advance.
 

Read other answers
RELEVANCY SCORE 51.6

Hello again everyone. I apologize in advance for the long post, my primary question starts and ends at the bold font way down there if you wanna skip to it.

I am going to start working on a way to combine all of our half a dozen excel sheets and separate, inconsistently named customer lists into one single file. My first idea is to use access as I have (extremely limited) experience with it. What I need to figure out is exactly HOW I am going to combine these excel sheets into one file.

The idea here is that I need to be able to track; Customer name/address, what we pick up or deliver to them, and individual records for every stop we do at that customer.
As it stands right now we have 6-7 different sheets that cover the various services we provide. Each one however is listed like vertically:

Customer Name/Address
*Price code(s)*
Date of pickup/amount picked up

As an example we might have something that looks like this:

Company X
CODE1234
01.01.11 125
01.02.11 250
01.03.11 120
(insert any number of pickups here)

So on and so forth with each different customer starting immediately below the last pickup. New pickups are entered by inserting a row, thus shifting everything else down. This results in many hundreds, on some lists a couple thousand rows.
The only way they are kept in order at the moment is that they are in alphabetical order. This is the way the previous manager did things in Excel. Needless to say it does not do us very good when attempting to obtain various ... Read more

A:Solved: Access 2007 project. Don't know how to structure this thing.

Read other 8 answers
RELEVANCY SCORE 51.2

i'm doing a project that is for a IT system and software, i need it so that every two weeks in project on a monday there is a meeting so none of the staff can work that day.

is there a way to have it so the meeting is always there and i dont have to put the task 'meeting' in the gantt chart and work it out manually every two weeks.

Rob
 

Read other answers
RELEVANCY SCORE 51.2

How do you insert dependences in Microsoft Project without changing the finish dates?

How would you put it if you say for example that "find similar football coaches" is dependent on "sending an e-mail to coach" finishing first?
 

Read other answers
RELEVANCY SCORE 51.2

I have Microsoft Project 98 and an older version (4.0). Project 98 is an upgrade so requires that I either have and older version installed or that I provide proof. Well here's the kicker....4.0 is on floppy and all I now have is disk 1 and my new laptop doesn't have a floppy drive. I've tried putting the floppy in a networked floppy drive but the installation claims it doesn't see the files. I also copied the files to my hard drive in a folder as well as to a CD. Nothing is working. Can you help me get past this?

Thanks
 

A:Microsoft Project 98

Man, this is a glitch! New PCs w/o floppy drives may be a pain for a lot of folks in similar situations.

Seems you have tried every logical approach...and that you'd need a full install of version 4.0 to do the ugrade. Any way you can find the other floppies for 4.0, do an install, and then go from there?

I'm interested to hear if there is some work around for this...academic, really, but interesting problem.
 

Read other 1 answers
RELEVANCY SCORE 51.2

I am using Office Professional Plus 2007 on Windows 7. I am syncing with iCloud.

Today while I was modifying an appointment, I suddenly lost all my appointments in the day/week/month view. I can still see them in the "All appointments" view.

Here is what I have tried:
run diagnostics
started outlook with the following switches: /cleanview, /resetfolders, /safemode,
reset filters on views
uninstalled-reinstalled
but the problem still exists. I should also mention when I reinstalled, my data was still there, so maybe there is something corrupt in my profile?

Can anyone help? Please! I have turned off syncing for my iPhone with the iCloud for the time being because I am terrified I am suddenly going to lose my calendar on my iPhone and then I will be screwed :-(
 

Read other answers
RELEVANCY SCORE 50.8

When trying to cut and paste cells from Excel 2003 into a Micrososft Project task list. (This project is published on a project central 2000 server). The CPU on the local computer hangs (100% utilization) The desktop version of the Project software is 2002 standard. The operating system is Windows XP SP1. This functionality has been used in the past and was previously working. No upgrades or changes have been made to the server environment. Copying text from the formula bar(excel) to the text line for the task entry does work, but is too cumbersome to make 100's of entries daily.

I searched Microsoft's support site and did not any knowledge base articles that address this issue.

The Project application can be stopped via the task manager, but changes have not been updated to the project central server.
 

Read other answers
RELEVANCY SCORE 50.8

Hi!

Quick question for project users. I'm updating hourly work (ie 4 or 8 hours etc.) in the project (the work column) and it only changes the duration column automatically when I mark the task complete. What am I doing wrong?
Thanks!
 

Read other answers
RELEVANCY SCORE 50.8

I have completed 2 documents on Microsoft Project 2003.

One of the documents will open but the other will not and comes up with the following message.

"Project cannot open file.

Check that the file name and the path is correct

Check that the file format is recognised by project

Project files saved in a version earlier than the microsoft project 98 cant be opened.

If your file is from an earlier version, open it in that version, click save as (file menu) and save in MPX format.
Open the MPX file in another version of project. When you use this method, project data is imported, but formatting is lost."

Dont fully understand what this is saying, but i have completed both documents on my PC using the same software.

Please Help